FAT evidence packet
| Gate | Agree before the test | Keep as evidence |
|---|---|---|
| Inputs | Approved bottles, caps, labels, product-water and pack materials | Sample identity, drawings, quantities and approvals |
| Run | Duration, output basis, allowed stops, reject handling and staffing | Time log, counters, stop log and observations |
| Quality | Fill, cap, code, label and pack checks with methods and tolerances | Measured results, instruments and sample record |
| Closeout | Deviation class, owner, correction, retest and release rule | Signed open-item and final acceptance record |
Questions to close before purchase
Which customer bottles, caps, labels and packing materials will be used?
Ask the supplier to answer in the quotation, technical agreement, drawing or responsibility schedule—not only in chat.
What run duration, output, stop, reject and quality criteria apply?
Ask the supplier to answer in the quotation, technical agreement, drawing or responsibility schedule—not only in chat.
How will deviations, corrective actions and retesting be documented?
Ask the supplier to answer in the quotation, technical agreement, drawing or responsibility schedule—not only in chat.
What you should leave with
- Pre-FAT document gate
- Machine and line test points
- Deviation-and-closeout record
Last reviewed: 2026-08-30. Technical values and equipment availability are project-specific unless explicitly identified as catalog-reference information.